a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

To reduce laboratory​ costs, water samples from twotwo public swimming pools are combined for one test for the presence of bacteria. Further testing is done onl
find the coefficient of Y^2 in the expansion of (2x+y)^3
What does it mean to focus a Karate technique?
Match each description to a character from Romeo and Juliet.
6. Identify these words as synonyms, antonyms, or homophones. allowed / aloud A. antonyms B. homophones C. synonyms
need help with 14 and 16 pls asap!! this is my friends test and im taking it tomorrow!!
What is the measure of the sector shaded above?
Please help I will amek brainliest
Both first and second language learners over-generalize. True False
what is the counter-argument of an persuasive essay?​