To complete a job a crew of 8 people needs 18 days. How long will the same job be finished if the crew will have 9 people?

Respuesta :

rockyrules789 rockyrules789
  • 01-11-2019

Answer:

16

Step-by-step explanation:

.

Answer Link
lajfoaofje lajfoaofje
  • 27-06-2020

Answer:

16

Step-by-step explanation:

Answer Link

Otras preguntas

At the first continental Congress which of the following did the congress demand of England
Which of the following is NOT true about structural adjustment programs (SAPs)? -SAPs often require recipient nations to concentrate more on trade and produc
[tex]F(x) = \frac{x^{3-8} }{x^{2} -6x+8}[/tex] What is the Domain: Holes: VA: HA: OH: Roots: Y-Intercept
Which choice is equivalent to the quotient shown here for acceptable values of x
Which choice is equivalent to the product below for when x>/ 0
How does DNA help with the transfer of genetic material from parents to offspring? A) Enzymes break down DNA, releasing amino acids that join to form proteins a
You are looking for part-time employment and posted your résumé to an online job site. One day you receive an e-mail from a company whose name you do not recogn
How does an atom of bromine-79 become a bromide ion with a -1 charge? A. The atom loses 1 proton to have a total of 34 B. The atom loses 1 protron to have a tot
This one, (linked picture)
Kenny bought a new car stereo that cost $220, but he had a coupon for a 14% discount. How much did Kenny pay for the car stereo.