A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

What would life be like without memes?
what is 175-(64-32)+(8÷3)÷200​
7 = -x+3. Consider the line y = Find the equation of the line that is parallel to this line and passes through the point (-5, 6). Find the equation of the line
Kevin and Randy Muiso have a jar containing 61 coins, all of which are either quarters or nickels. The total value of the coins in the jar is $12.05. How many o
There are 12 girls and 10 boys in the student council. What is the ratio of the number of girls to the total number of members? F. 6:5. G. 5 to 6. H. 6 to 11. I
The growth of skeletal bones is controlled by a hormone from the:
Which american bird does not migrate south?
Find the GCF and LCM of 217x328x11 and 213x345x74and explain your reasoning.
Goods in the economy continue to be shipped by rail and water. True False
What is the slope-intercept form of y + 6 = 2(x + 2)?