Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

name two causes of ww2
The war Refugee Board, established by president Roosevelt, worked
Grandma made an apple pie. Josh and his brother joe finished 4/5 of it. Then 3 friends came over and shared the left over. How much pie did each friend eat
What weakness did Delaware’s at the constitutional convention see in the articles of confederation
the two types of stress are
It takes Evan 6 3/4 to mow 3 lawns. It takes 2 1/3 hours to mow me. Gals lawn and 1 3/4 hot mow Ms. Lee’s lawn. How many hours does it take Evan to mow the thir
A square is dilated by a scale factor of 1.25 to create a new square. How does the area of the new square compare with the area of the original square? A)The a
Who was not a famous harlem renaissance Artist during the 1920s
Who killed the electric car video discussion questions answers?
As I finished my dance, the audience jumped to their feet and began to clap. “That was great, Marcie!” a freshman yelled. ”You’re amazing!” screamed another. M