A piece of work takes 20 labourers to complete in 10 days. how many labourers will complete the same job in 25 days if they work at the same rate?​

Respuesta :

denimjackets23
denimjackets23 denimjackets23
  • 04-09-2021

Step-by-step explanation:

If 20 labourers=10 days

x labourers = 25 days

10x= 25×20

[tex] \frac{10x}{10} = \frac{25 \times 20}{10}[/tex]

Cancelling out by 10 on both sides

[tex]x = \frac{25 \times 2}{1} \\ x = 50 [/tex]

Therefore, it takes 50 labourers to complete the work at the same rate in 25 days.

Answer Link

Otras preguntas

(10y^3+20y^2+55y)/5y
Data are drawn from a symmetric and bell shaped distribution with a mean of 120 and a standard deviation of 5. There are 900 observations in the data set. What
How were life forms affected by the rise in atmospheric oxygen levels that began 2.2 billion years ago?
Find Domain of the functionsquare root of (x-8)/x(x-9)
Scarcity is the condition of not having enough goods and services to satisfy everyone's?
Can someone use the word delta in a sentence
Marika and Freddy sold 70 homes for Ron Realty. If Marika sold 2.5 times as many homes as Freddy, how many homes did each sell?
Which equation has the same y-intercept as y=4x-3?a. y-3=x              b. y=8x+3    c. 3-y=4x      d. y=-3+8xWhich of the following is the equation of the line
Scarcity is the condition of not having enough goods and services to satisfy everyone's?
Scarcity is the condition of not having enough goods and services to satisfy everyone's?