It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

What is the main difference between food chains and food webs brainly.
please help!!I'll make you brainliest ​
Hi there I need help and thx How many kilobytes are in 100 gigabytes
What is the correct equation to solve for x?
What percentage is the fraction equal to?
QUESTION ON PIC TY!!!
What different approaches do Lord Redesdale and Ryunosuke Akutagawa take to writing about Buddhism? (60 POINTS!!)
One number exceeds another by 5. The sum of the numbers is 49. What are the​ numbers?
Can someone please help me? :(
what is the selling price of a pair of $40 skates with a 25% discount?