If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

Write a paragraph explaining what the words below have in common. a. minuteman b. Loyalist c. Patriot
Where does digestion take place
read this opening lines of Sojourner Truth's speech "Ain't Ia Woman what tone do these lines convey
who were the federalist?
What is the surface area of this design
Naomi’s calm leadership style saw the team through dozens of what A.crises B.crisises C.crisis
What are three important documents to the us government?
Let f(x)= x^2 + 5. Find formulas for f(f(x)) and f(f(f(x)))
Which is one clue that "Close Encounters of the Bear Kind" is a work of nonfiction?   A. The article cites a particular study done in Alaska.   B. The ar
How do you convert the repeating digit 0.285714... to a fraction?