Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

When a pitcher is holding a baseball, the ball has ______ energy. nuclear heat potential kinetic
Which property would be characteristic of a non-metal? A. shiny B. powdery C. malleable D. conducts electricity
6 4/5 - 2 1/5 is what?
Which type of fault has motion that occurs in a sideways fashion? A. normal B. reverse C. transform D. normal and reverse
What is a religious group?
name a pair of fractions that use the least common denominator and are equivalent to 9/10 + 5/6
It is important to wear proper protective equipment in lab even when not actively performing experiments because accidents can affect any researcher, even one n
Based on the lesson, individuals who broke away from the Catholic Church were known as _____.
What is a religious group?
is the statement "line plots display individual data" true or false?